21. A is 50% as efficient as B. C is half as efficient as A and B together. If C alone does the work in 40 days, then A ,B and C together can complete the work in:

A. 13 1/3 days

B. 15 days

C. 16 2/3 days

D. 20 days

Discuss Work Space

Answer: option a

Explanation:

If B does 4 unit/day, then, A does 2 unit/day and C does 3 unit/day.
Total work = 40 x 3 = 120 unit
Working together, they can do it in 120/9 = 40/3 days.


22. After working for 6 days, Abhi finds that only 1/3 rd of the work has been done. He employs Biswas who is 60% as efficient as Abhi. How many days more would Biswas take to complete the work?

A. 18 days

B. 19 days

C. 20 days

D. 21 days

Discuss Work Space

Answer: option c

Explanation:

Abhi does the work in 6 x 3 = 18 days
Biswas does it in 18/(0.6) = 30 days
Let total work is 90.
Biswas does 3 unit/day and Abhi 5 unit/day.
Abhi has done 30 unit in 6 days and 60 unit is left.
Biswas will complete it in 60/3 = 20 days


23. Akhil and Bishnu working together completed a job in 5 days. If Akhil worked with twice of his efficiency and Bishnu worked with 1/3 rd of his efficiency, the work would have been completed in 3 days. Akhil alone could complete the work in:

A. 6 days

B. 25/4 days

C. 15/2 days

D. 8 days

Discuss Work Space

Answer: option b

Explanation:

Let Akhil does x unit/day and Bishnu 3y unit/day.
Given, Total work = 5(x + 3y) = 3(2x + y)
=> x = 12y
Work done by Akhil alone in [5(x + 3y)]/x = 75y/12y = 25/4 days


24. 12 men can complete a job in 12 days. How many extra days will be needed to complete the job if 6 men leave after working for 6 days?

A. 3

B. 6

C. 9

D. 12

Discuss Work Space

Answer: option b

Explanation:

Man days to complete the job = 12 x 12 = 144
6 men in 6 days completed = 36 job
Job left = 144 - 36 = 108
Number of days required to complete this job = 108/6 = 18
So, 6 more men are needed.


25. 20 men completed one-third of a job in 20 days. How many more men should be employed to finish the rest of the work in 25 more days?

A. 10

B. 12

C. 15

D. 18

Discuss Work Space

Answer: option b

Explanation:

Work done = 20 x 20 = 400 men-days (1/3 rd)
Work left = 800
men needed for this = 800/25 = 32
So, (32 - 20) = 12 more men are needed.



Time and Work Questions and Answers FAQ

Read FAQ

Why do I need to learn Time and Work Questions with Answers in Quantitative Aptitude?

Time and Work is an important topic of Quantitative Aptitude. MCQ type Questions with Answers of Time and Work are required to build your Quantitative Aptitude skills which is a prerequisite for your Career development.

How Time and Work MCQ type Questions with Answers is helpful in my Career?

The Quantitative Aptitude MCQ type Questions with Answers based on "Time and Work" will help you improve your skills in order to face the interviews, crack Campus recruitment tests and various other competitive examination such as CAT, GATE, GRE, MAT, Bank Exam, Railway Exam etc. with full confidence.

What is the best way to prepare for Time and Work Questions with Answers?

First, go through the basic concepts related to Time and Work. Be ready with all Important Points of Time and Work. Then, attempt questions. Besthai.in provides you lots of fully solved Time and Work MCQ type questions and answers with explanation. It will help you to grasp the whole topic Time and Work in the easy way.

How this online resource is helpful in my preparation for Time and Work Questions and Answers?

Besthai.in provides lots of fully solved MCQs of Time and Work. You can study all important points related to Time and Work. You can also take Online Test to check your preparation for Time and Work in Quantitative Aptitude.

Subscribe for Latest Career Trends
Subscribe Now
Use AI and ChatGPT for Career Guidance

Unlock Your Future

Join Now
Worried for Placements in 2024?

Join FAST TRACK Course

Join Now
Supercharge Your SUCCESS

Join All in One Placement Mock Tests-2024

Join Now